Tendering a workplace partner: the selection criteria that really matter.

    By Mark van den Berg

    A tender for a workplace partner often runs in practice on the two most easily measurable criteria: price and references. Both are relevant; both are insufficient. This article describes which criteria really matter at an investment from €5M upwards — and how a tender process is structured so that the right partner can be chosen, not just the cheapest.

    Three types of partners, three different tenders

    A workplace project typically calls for three different partners: a strategic adviser (workplace strategy, business case), an architect/design party, and an executing party (design & build or traditional contractor). For each type, the selection criteria are fundamentally different.

    For strategist: industry insight, board experience, independence. For designer: portfolio, design philosophy, chemistry with the board. For contractor: organisational strength, cost control, project leadership. Those who tender all three with the same criteria framework get suboptimal partners.

    The six criteria beyond price and CV

    Six criteria that are structurally underexposed in standard tenders:

    • Seniority of the actual project team (not the pitch squad).
    • Capacity and backlog — what else is on the party's table?
    • Culture match with the own organisation — directness, language register, speed.
    • Willingness to challenge — partners who only say yes cost money.
    • Degree of independence from suppliers (especially in D&B).
    • Track record at comparable scale and sector, not just references.

    The pitch team is almost never the project team

    At large parties, we see structurally that the partner-and-senior-director who does the pitch is replaced after award by an associate-led team. This should be an explicit part of the tender questions: 'Who actually sits at the table after award, for how many hours per week, for what duration?' — with names, not job titles.

    The same applies to executing parties: the director or project manager who bids is often not the one who does the work. This is not bad faith, but it is a structural pattern that must be caught at procurement.

    Price in context — not as a decisive criterion

    A difference of 10 to 15 percent in price between parties at this stage is almost always smaller than the return on the right partner choice over the entire project. We regularly see that a 12 percent cheaper party produces 25 percent more cost overruns during execution. The tender should therefore consciously depart from pure lowest-price logic.

    Good practice: price weighted at maximum 30 percent in scoring. The rest goes to substantive and collaboration criteria. For design & build projects, this is extra crucial, because the partner makes both design and execution decisions.

    How 'chemistry' can be tested

    Chemistry between board and partner is a serious criterion but elusive in a tender document. A workable approach: a second tender round with a joint design session of 3 to 4 hours, in which finalists work with the board on a real sub-problem. That reveals working style, depth of thought and collaboration dynamics more than ten pitches.

    Frequently asked questions

    How many parties to invite?

    +

    For strategist: 3 (longlist 6). For architect: 4 to 5 (longlist 8 to 10). For contractor: 3 to 4 (longlist 5 to 6). More leads to pitch fatigue and lower quality bids.

    How long does a serious tender take?

    +

    Strategist: 4 to 6 weeks. Architect: 8 to 12 weeks. Contractor: 10 to 14 weeks. Shorter than this comes at the expense of bid quality.

    Does EU tendering apply to private organisations?

    +

    Not required unless subsidy or public capital is received. However, the discipline of the MEAT framework can be useful even for private assignments — especially for quality objectification.

    Who writes the tender document?

    +

    Ideally the strategic adviser (who has no interest in award to design/execution) or a specialised procurement adviser. Not the party that wants to bid itself.

    Also available in Dutch.
    Continue reading
    Related articles
    Strategy Session

    Before the first decision is made.

    A strategy session is the moment to clarify your context and the strategic choices around your workspace investment — before design and construction set the direction.